Telecommunications Duct Bank Replacement

Back to Listing

Outdoor Site

Outdoor Site

Campus:
IU Bloomington

Completion Date
December 5, 2008

Project Type:
Renovation

Primary Use:
Utilities

Architect:
MNA

Team Leader:
Koryta

Project Budget

  • Internal funding: $2000000
  • Total budget: $2000000

Project Description

This project involved the installation of a duct bank along the south edge of Seventh Street, along the west edge of Union Street, and through the west side of the parking lot east of Eigenmann Hall. A steel sleeve under the railroad was installed for routing conduits. Twenty four-inch ducts were installed in the duct bank.